Elmsall Way Warehouse is an operational 2.4 MW solar farm in Wakefield, generating since 9 July 2021. Planning permission was granted on 7 May 2020, 5 months after submission. Operator of record: Next Distribution.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 9 July 2021
Solar Photovoltaics
Technology
Next Distribution
Wakefield
Authority
England

Planning and build timeline

Application submitted18 December 2019
Permission granted7 May 2020
5 months after submission
Operational9 July 2021
14 months after consent

Screening a site of your own?

RedlineUK · £39

Wakefield approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Elmsall Way Warehouse’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wakefield’s record on solar

Wakefield has decided 33 solar farms and approved 94%, taking a median of 1.8 months. See every solar farm decision in Wakefield

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
30.3 km
Landfill Gas · Operational
2.12.7 km
Wind Onshore · Operational
83 km
Anaerobic Digestion · Operational
64.6 km
Solar Photovoltaics · Under Construction
2.56.6 km
Solar Photovoltaics · Operational
57.6 km
Wind Onshore · Operational
87.9 km
Solar Photovoltaics · Operational
1.58.6 km

How big is Elmsall Way Warehouse?

Elmsall Way Warehouse has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Elmsall Way Warehouse?

REPD records the operator as Next Distribution. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Elmsall Way Warehouse approved and built?

The application was submitted on 18 December 2019. Permission was granted on 7 May 2020, 5 months later. The site became operational on 9 July 2021, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7735.