Manor Farm (Farm AD) is an operational 1.5 MW anaerobic digestion plant in South Holland, generating since 31 December 2013. Planning permission was granted on 5 May 2011, 2 months after submission. Operator of record: Biogen (formerly Tamar Energy).

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 31 December 2013
Anaerobic Digestion
Technology
Biogen (formerly Tamar Energy)
South Holland
Authority
England

Planning and build timeline

Application submitted17 March 2011
Permission granted5 May 2011
2 months after submission
Operational31 December 2013
32 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Holland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Manor Farm (Farm AD)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
121.7 km
Solar Photovoltaics · Operational
1.76.2 km
Solar Photovoltaics · Operational
16.2 km
Solar Photovoltaics · Operational
12.710.2 km
Wind Onshore · Operational
1411 km
Solar Photovoltaics · Operational
49.911.5 km
Battery · Under Construction
25013.4 km
Landfill Gas · Operational
1.314 km

How big is Manor Farm (Farm AD)?

Manor Farm (Farm AD) has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Manor Farm (Farm AD)?

REPD records the operator as Biogen (formerly Tamar Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Manor Farm (Farm AD) approved and built?

The application was submitted on 17 March 2011. Permission was granted on 5 May 2011, 2 months later. The site became operational on 31 December 2013, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 282.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode