Renewable sites › MALMAYNES HALL FARM
MALMAYNES HALL FARM
MALMAYNES HALL FARM is operational in Medway with a recorded capacity of 12 MW, and has been generating since 2015-03-31.
Planning and build timeline
| Application submitted | 2014-07-31 |
| Permission granted | 2014-11-06 3 months after submission |
| Operational | 2015-03-31 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Medway’s record on solar
Medway has decided 10 solar farms and approved 90%, taking a median of 2.4 months. See every solar farm decision in Medway →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Shakespeare Farm Landfill Site Landfill Gas · Operational | 1 | 1 km |
Port of Sheerness Wind Farm (was Lappel Bank) Wind Onshore · Operational | 8.2 | 9.4 km |
Iwade Solar Farm Solar Photovoltaics · Operational | 1.7 | 10.2 km |
Tesco Super-Store (Bridge Road) Solar Photovoltaics · Operational | 0.4 | 10.2 km |
Orchard Farm Solar Photovoltaics · Operational | 10 | 11.2 km |
Pitsea Landfill Scheme Landfill Gas · Operational | 11.6 | 11.6 km |
Pitsea Tipp Landfill Gas · Operational | 14 | 11.7 km |
Land off Queenborough Road Battery · Under Construction | 40 | 11.9 km |
How big is MALMAYNES HALL FARM?
MALMAYNES HALL FARM has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates MALMAYNES HALL FARM?
REPD records the operator as Wessex Solar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was MALMAYNES HALL FARM approved and built?
The application was submitted on 2014-07-31. Permission was granted on 2014-11-06, 3 months later. The site became operational on 2015-03-31, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2135.