Port of Sheerness Wind Farm (was Lappel Bank) is operational in Swale with a recorded capacity of 8.2 MW, and has been generating since 2016-09-20.

8.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-09-20
Wind Onshore
Technology
Peel Energy
Swale
Authority
England

Planning and build timeline

Application submitted2008-08-26
Permission granted2009-03-11
6 months after submission
Operational2016-09-20
90 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Tesco Super-Store (Bridge Road)
Solar Photovoltaics · Operational
0.40.8 km
Land off Queenborough Road
Battery · Under Construction
404.1 km
South Lees Farm
Solar Photovoltaics · Operational
116.1 km
Ridham CHP Plant
Biomass (dedicated) · Operational
256.8 km
Morrisons roof mounted solar
Solar Photovoltaics · Operational
27.9 km
Kemsley Substation
Battery · Operational
49.98.5 km
K3 CHP Facility (Kemsley EfW)
EfW Incineration · Operational
49.98.5 km
Orchard Farm
Solar Photovoltaics · Operational
108.8 km

How big is Port of Sheerness Wind Farm (was Lappel Bank)?

Port of Sheerness Wind Farm (was Lappel Bank) has a recorded installed capacity of 8.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Port of Sheerness Wind Farm (was Lappel Bank)?

REPD records the operator as Peel Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Port of Sheerness Wind Farm (was Lappel Bank) approved and built?

The application was submitted on 2008-08-26. Permission was granted on 2009-03-11, 6 months later. The site became operational on 2016-09-20, 90 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3738.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council