Iwade Solar Farm is operational in Swale with a recorded capacity of 1.7 MW, and has been generating since 2015-03-19.

1.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-19
Solar Photovoltaics
Technology
FH Dean Ltd
Swale
Authority
England

Planning and build timeline

Application submitted2013-01-17
Permission granted2013-07-11
6 months after submission
Operational2015-03-19
20 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Swale’s record on solar

Swale has decided 26 solar farms and approved 96%, taking a median of 2.5 months. See every solar farm decision in Swale

Other built sites within 15 km

SiteMWDistance
Bobbing solar farm
Solar Photovoltaics · Operational
11.32.6 km
Orchard Farm
Solar Photovoltaics · Operational
103.1 km
Kemsley Substation
Battery · Operational
49.96.2 km
Morrisons roof mounted solar
Solar Photovoltaics · Operational
26.4 km
K3 CHP Facility (Kemsley EfW)
EfW Incineration · Operational
49.97.3 km
Ridham CHP Plant
Biomass (dedicated) · Operational
257.5 km
Plot 2B EurolinkV
Battery · Under Construction
208.3 km
Tonge Corner Farm
Solar Photovoltaics · Operational
228.9 km

How big is Iwade Solar Farm?

Iwade Solar Farm has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Iwade Solar Farm?

REPD records the operator as FH Dean Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Iwade Solar Farm approved and built?

The application was submitted on 2013-01-17. Permission was granted on 2013-07-11, 6 months later. The site became operational on 2015-03-19, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4836.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council