Renewable sites › Maerdy
Maerdy
Maerdy is operational in Rhondda Cynon Taf with a recorded capacity of 24 MW, and has been generating since 2013-08-31.
Planning and build timeline
| Application submitted | 2006-09-01 |
| Permission granted | 2008-02-10 17 months after submission |
| Operational | 2013-08-31 67 months after consent |
Rhondda Cynon Taf’s record on onshore wind
Rhondda Cynon Taf has decided 13 onshore wind schemes and approved 92%, taking a median of 23.1 months. See every onshore wind scheme decision in Rhondda Cynon Taf →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Mynydd Bwllfa Wind Farm - Resubmission Wind Onshore · Operational | 22.5 | 2 km |
Brynpica Landfill Site Landfill Gas · Operational | 2.7 | 5 km |
Rhigos Road - Solar Farm Solar Photovoltaics · Under Construction | 9.88 | 5.1 km |
Hirwaun Stor Generation - Battery Storage Battery · Operational | 21.76 | 5.3 km |
Bryngolwg Farm, Hirwaun - Solar farm Solar Photovoltaics · Operational | 8.94 | 5.7 km |
Enviroparks Hirwaun Generation Site Advanced Conversion Technologies · Operational | 20 | 6 km |
Penrhys Wind Farm/Ferndale Power Factory Wind Onshore · Operational | 6.4 | 6.9 km |
Hendre Fawr Farm Solar Photovoltaics · Operational | 11.6 | 7 km |
How big is Maerdy?
Maerdy has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Maerdy?
REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Maerdy approved and built?
The application was submitted on 2006-09-01. Permission was granted on 2008-02-10, 17 months later. The site became operational on 2013-08-31, 67 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4138.