Renewable sites › Hendre Fawr Farm
Hendre Fawr Farm
Hendre Fawr Farm is operational in Neath Port Talbot with a recorded capacity of 11.6 MW, and has been generating since 2015-03-06.
Planning and build timeline
| Application submitted | 2013-09-18 |
| Permission granted | 2014-07-06 10 months after submission |
| Operational | 2015-03-06 8 months after consent |
Neath Port Talbot’s record on solar
Neath Port Talbot has decided 12 solar farms and approved 100%, taking a median of 5.7 months. See every solar farm decision in Neath Port Talbot →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bryngolwg Farm, Hirwaun - Solar farm Solar Photovoltaics · Operational | 8.94 | 2.6 km |
Rhigos Road - Solar Farm Solar Photovoltaics · Under Construction | 9.88 | 3.2 km |
Maesgwyn solar farm Solar Photovoltaics · Operational | 7.5 | 3.5 km |
Hirwaun Stor Generation - Battery Storage Battery · Operational | 21.76 | 3.5 km |
Maesgwyn Wind Farm - extension Wind Onshore · Operational | 2.5 | 3.7 km |
Enviroparks Hirwaun Generation Site Advanced Conversion Technologies · Operational | 20 | 3.8 km |
Maesgwyn Wind Onshore · Operational | 26 | 4.7 km |
Mynydd Bwllfa Wind Farm - Resubmission Wind Onshore · Operational | 22.5 | 6.3 km |
How big is Hendre Fawr Farm?
Hendre Fawr Farm has a recorded installed capacity of 11.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hendre Fawr Farm?
REPD records the operator as INRG Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hendre Fawr Farm approved and built?
The application was submitted on 2013-09-18. Permission was granted on 2014-07-06, 10 months later. The site became operational on 2015-03-06, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2286.