Brynpica Landfill Site

Brynpica Landfill Site is an operational 2.7 MW landfill gas site in Rhondda Cynon Taf, generating since 1 August 2003. Planning permission was granted on 20 March 2003, 2 months after submission. Operator of record: NOVERA.

2.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2003
Landfill Gas
Technology
NOVERA
Rhondda Cynon Taf
Authority
Wales

Planning and build timeline

Application submitted9 January 2003
Permission granted20 March 2003
2 months after submission
Operational1 August 2003
4 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Rhondda Cynon Taf: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Brynpica Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
6.42.3 km
Wind Onshore · Under Construction
1.52.6 km
Wind Onshore · Operational
245 km
Wind Onshore · Operational
255.2 km
Wind Onshore · Operational
105.3 km
Wind Onshore · Operational
17.55.8 km
Wind Onshore · Operational
22.56.6 km
Solar Photovoltaics · Operational
4.77.2 km

How big is Brynpica Landfill Site?

Brynpica Landfill Site has a recorded installed capacity of 2.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Brynpica Landfill Site?

REPD records the operator as NOVERA. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Brynpica Landfill Site approved and built?

The application was submitted on 9 January 2003. Permission was granted on 20 March 2003, 2 months later. The site became operational on 1 August 2003, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 665.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode