Planning and build timeline
| Application submitted | 2022-06-15 |
| Permission granted | 2022-06-27 0 months after submission |
| Operational | not recorded |
Rhondda Cynon Taf’s record on solar
Rhondda Cynon Taf has decided 13 solar farms and approved 100%, taking a median of 5 months. See every solar farm decision in Rhondda Cynon Taf →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rhigos Road - Solar Farm Solar Photovoltaics · Under Construction | 9.88 | 0.7 km |
Hirwaun Stor Generation - Battery Storage Battery · Operational | 21.76 | 0.9 km |
Enviroparks Hirwaun Generation Site Advanced Conversion Technologies · Operational | 20 | 1.2 km |
Hendre Fawr Farm Solar Photovoltaics · Operational | 11.6 | 2.6 km |
Mynydd Bwllfa Wind Farm - Resubmission Wind Onshore · Operational | 22.5 | 4.5 km |
Maesgwyn solar farm Solar Photovoltaics · Operational | 7.5 | 5.2 km |
Maerdy Wind Onshore · Operational | 24 | 5.7 km |
Maesgwyn Wind Farm - extension Wind Onshore · Operational | 2.5 | 6.3 km |
How big is Bryngolwg Farm, Hirwaun - Solar farm?
Bryngolwg Farm, Hirwaun - Solar farm has a recorded installed capacity of 8.94 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bryngolwg Farm, Hirwaun - Solar farm?
REPD records the operator as Enviromena Asset Management UK Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bryngolwg Farm, Hirwaun - Solar farm approved and built?
The application was submitted on 2022-06-15. Permission was granted on 2022-06-27, 0 months later. REPD does not record an operational date.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11509.