Renewable sites › Rhigos Road - Solar Farm
Rhigos Road - Solar Farm
Rhigos Road - Solar Farm is under construction in Rhondda Cynon Taf with a recorded capacity of 9.88 MW.
Planning and build timeline
| Application submitted | 2023-11-24 |
| Permission granted | 2024-06-13 7 months after submission |
| Operational | not recorded |
Rhondda Cynon Taf’s record on solar
Rhondda Cynon Taf has decided 13 solar farms and approved 100%, taking a median of 5 months. See every solar farm decision in Rhondda Cynon Taf →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hirwaun Stor Generation - Battery Storage Battery · Operational | 21.76 | 0.4 km |
Bryngolwg Farm, Hirwaun - Solar farm Solar Photovoltaics · Operational | 8.94 | 0.7 km |
Enviroparks Hirwaun Generation Site Advanced Conversion Technologies · Operational | 20 | 1.2 km |
Hendre Fawr Farm Solar Photovoltaics · Operational | 11.6 | 3.2 km |
Mynydd Bwllfa Wind Farm - Resubmission Wind Onshore · Operational | 22.5 | 3.8 km |
Maerdy Wind Onshore · Operational | 24 | 5.1 km |
Maesgwyn solar farm Solar Photovoltaics · Operational | 7.5 | 6 km |
Maesgwyn Wind Farm - extension Wind Onshore · Operational | 2.5 | 6.8 km |
How big is Rhigos Road - Solar Farm?
Rhigos Road - Solar Farm has a recorded installed capacity of 9.88 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rhigos Road - Solar Farm?
REPD records the operator as Regener8 Power / Environmena. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rhigos Road - Solar Farm approved and built?
The application was submitted on 2023-11-24. Permission was granted on 2024-06-13, 7 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11384.
Novarly Parcel · official public data, read properly · parcel.novarly.com