Rhigos Road - Solar Farm

Rhigos Road - Solar Farm is a 9.88 MW solar farm under construction in Rhondda Cynon Taf. Planning permission was granted on 13 June 2024, 7 months after submission. Operator of record: Regener8 Power / Environmena.

9.88 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Regener8 Power / Environmena
Rhondda Cynon Taf
Authority
Wales

Planning and build timeline

Application submitted24 November 2023
Permission granted13 June 2024
7 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Rhondda Cynon Taf approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Rhigos Road - Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Rhondda Cynon Taf’s record on solar

Rhondda Cynon Taf has decided 13 solar farms and approved 100%, taking a median of 5 months. See every solar farm decision in Rhondda Cynon Taf

Other built sites within 15 km

SiteMWDistance
Battery · Operational
21.760.4 km
Solar Photovoltaics · Operational
8.940.7 km
Advanced Conversion Technologies · Operational
201.2 km
Solar Photovoltaics · Operational
11.63.2 km
Wind Onshore · Operational
22.53.8 km
Wind Onshore · Operational
245.1 km
Solar Photovoltaics · Operational
7.56 km
Wind Onshore · Operational
2.56.8 km

How big is Rhigos Road - Solar Farm?

Rhigos Road - Solar Farm has a recorded installed capacity of 9.88 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Rhigos Road - Solar Farm?

REPD records the operator as Regener8 Power / Environmena. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Rhigos Road - Solar Farm approved and built?

The application was submitted on 24 November 2023. Permission was granted on 13 June 2024, 7 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11384.