Renewable sites › Lyreco - Telford Distribution Centre
Lyreco - Telford Distribution Centre
Lyreco - Telford Distribution Centre is operational in Telford and Wrekin with a recorded capacity of 3.8 MW, and has been generating since 2016-01-26.
Planning and build timeline
| Application submitted | not recorded |
| Permission granted | not recorded |
| Operational | 2016-01-26 |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Telford and Wrekin’s record on solar
Telford and Wrekin has decided 23 solar farms and approved 100%, taking a median of 2.3 months. See every solar farm decision in Telford and Wrekin →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Granville Road Solar Farm Solar Photovoltaics · Operational | 5 | 0.7 km |
Granville Landfill Site Landfill Gas · Operational | 1.4 | 0.9 km |
Ricoh UK Products Solar Photovoltaics · Operational | 1.2 | 2.6 km |
Sheriffhales Solar Farm Solar Photovoltaics · Operational | 8.2 | 3.6 km |
Twitch Hill, Cheswell Grange Farm - Solar Farm & Battery Storage Battery · Under Construction | — | 4.4 km |
Twitch Hill, Cheswell Grange Farm - Solar Farm & Battery Storage Solar Photovoltaics · Under Construction | 25 | 4.4 km |
Wheat Leasows Solar Park Solar Photovoltaics · Operational | 4 | 4.6 km |
Steeraway Farm - Solar Farm Solar Photovoltaics · Under Construction | 30 | 6.5 km |
How big is Lyreco - Telford Distribution Centre?
Lyreco - Telford Distribution Centre has a recorded installed capacity of 3.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lyreco - Telford Distribution Centre?
REPD records the operator as Addison Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lyreco - Telford Distribution Centre approved and built?
REPD does not record a submission date. REPD does not record a grant date. The site became operational on 2016-01-26.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5602.