Renewable planning SolarTelford and Wrekin

Solar planning in Telford and Wrekin

Telford and Wrekin has decided 23 solar farms and approved 100% of them, taking a median of 2.3 months to decide. Consented capacity: 208 MW. 4 applications still awaiting a decision.

100%
Approved
23 granted · 0 refused
2.3 mo
Median decision
UK 2.3 mo
208 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

How Telford and Wrekin compares

Against the 298 UK authorities with 5+ solar decisions, Telford and Wrekin sits in the 77th percentile for approval rate (7 points above the England average) and the 51st percentile for speed.

Decisions by year

510Approved — 1 (2014)114Approved — 3 (2015)315Approved — 1 (2020)120Approved — 1 (2021)121Approved — 6 (2022)622Approved — 5 (2023)523Approved — 1 (2024)124Approved — 4 (2025)425
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (27)

SchemeMWStatusDecided
Kraft Heinz, Hortonwood - Solar Panels
H.J. Heinz Manufacturing UK Limited · TWC/2026/0190
0.81Application Submitted2026-03-16
Telford Shopping Centre, Northfield Street - Solar Panels
Olympus Power · TWC/2026/0101
0.58Application Submitted2026-02-10
Lyreco, Donnington Wood - Solar Panels
Private Developer · TWC/2025/0749 · 1 mo to decide
3.8Awaiting Construction2025-12-03
Tiddiecross Lane, Charlton - Tiddiecross Solar Farm & Battery Storage
Boultbee Brooks Renewables Walkford Moor Limited · TWC/2024/0909 · 5.8 mo to decide
14Awaiting Construction2025-06-06
TCL Packaging, Stafford Park - Solar Panels
My Power UK Limited · TWC/2025/0260 · 1 mo to decide
0.53Awaiting Construction2025-04-30
Makita Manufacturing Europe - Solar Panels
Makita Manufacturing Europe Limited · TWC/2024/0896 · 1 mo to decide
0.17Awaiting Construction2025-01-07
Furrows Ford Store, Furrows Business Park - Solar Panels
Furrows Limited · TWC/2024/0616 · 1.3 mo to decide
0.27Awaiting Construction2024-09-17
Mail Solutions - Solar Panels
Ylem Energy Limited · TWC/2024/0402
0.6Application Submitted2024-05-20
Telford Ten Pin, International Way - Solar PV Panels
Telford Ten Pin · TWC/2023/0685 · 0.9 mo to decide
0.23Awaiting Construction2023-10-09
Telford Shopping Centre, Woodhouse Central - Solar Photovoltaic Panels
Olympus Power · TWC/2023/0628 · 0.8 mo to decide
0.7Awaiting Construction2023-09-18
High Ercall Solar Farm
Assured Asset Solar 1 Limited · TWC/2023/0064 · 6.8 mo to decide
49.9Awaiting Construction2023-08-22
Sugden Farm - Solar Panels
GH & U Davies & Son Ltd · TWC/2023/0325 · 3.1 mo to decide
0.44Awaiting Construction2023-08-18
Steeraway Farm - Solar Farm
Enviromena · TWC/2021/1071 · 18.3 mo to decide
30Under Construction2023-05-09
Greenhous Village, Osbaston - Solar Panels
Private Developer · TWC/2022/0814 · 1.6 mo to decide
0.81Awaiting Construction2022-11-14
Parkside Court - Solar Panels & Air Source Heat Pumps
Government Property Agency · TWC/2022/0555 · 1.1 mo to decide
0.27Awaiting Construction2022-08-03
Wz Packaging, Halesfield - Solar Panels
Cactus Energy · TWC/2022/0556 · 0.9 mo to decide
0.52Awaiting Construction2022-07-27
Makita Manufacturing Europe - Solar Photovoltaic Panels
Makita Manufacturing Europe · TWC/2022/0489 · 0.7 mo to decide
0.39Awaiting Construction2022-07-01
Twitch Hill, Cheswell Grange Farm - Solar Farm & Battery Storage
Ethical Power · TWC/2021/1225 · 6.2 mo to decide
25Under Construction2022-06-29
Telford Shopping Centre - Solar Photovoltaic PV Array
Telford Trustee No.1 Limited · TWC/2021/1135 · 1.8 mo to decide
1.82Awaiting Construction2022-01-21
New Works Lane - Solar Farm
Greentech · TWC/2021/0737
30Application Submitted2021-07-23
Myttons Solar Farm
JBM Solar Projects Limited · TWC/2020/0851 · 5.2 mo to decide
49.9Awaiting Construction2021-03-15
Ricoh UK Products
Push Energy · TWC/2020/0293 · 4.9 mo to decide
1.2Operational2020-08-28
Granville Road Solar Farm
Solstice Renewables · TWC/2015/0804 · 3.1 mo to decide
5Operational2015-12-11
Rushmoor Lane Farm (Cheshire Coppice)
Sunsave 38/ Vogt Solar · TWC/2015/0560 · 3.9 mo to decide
5Operational2015-10-13
Tiddiecross Solar Farm
Vogt Solar · TWC/2014/0810 · 3.9 mo to decide
10.5Operational2015-01-07
Wheat Leasows Solar Park
Telford and Wrekin Borough Council · TWC/2014/0134 · 2.8 mo to decide
4Operational2014-05-08
Lyreco - Telford Distribution Centre
Addison Energy
3.8Operational

Does Telford and Wrekin approve solar farms?

Yes — of the 23 solar farms Telford and Wrekin has decided, 100% were approved (23 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Telford and Wrekin?

The median time from application to decision is 2.3 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Telford and Wrekin consented?

208 MW has been consented across 23 approved schemes. A further 4 applications awaits a decision.

Other technologies in Telford and Wrekin

Battery storage in Telford and WrekinOnshore wind in Telford and Wrekin

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.