Granville Landfill Site

Granville Landfill Site is an operational 1.4 MW landfill gas site in Telford and Wrekin, generating since 1 October 1999. Planning permission was granted on 1 July 1994, 2 months after submission. Operator of record: Biogas Technology Ltd/Natural Power.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 October 1999
Landfill Gas
Technology
Biogas Technology Ltd/Natural Power
Telford and Wrekin
Authority
England

Planning and build timeline

Application submitted30 April 1994
Permission granted1 July 1994
2 months after submission
Operational1 October 1999
63 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Telford and Wrekin: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Granville Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.5 km
Solar Photovoltaics · Operational
3.80.9 km
Solar Photovoltaics · Operational
1.22.6 km
Solar Photovoltaics · Operational
8.22.7 km
Battery · Under Construction
4.7 km
Solar Photovoltaics · Under Construction
254.7 km
Solar Photovoltaics · Operational
45.5 km
Solar Photovoltaics · Under Construction
307.4 km

How big is Granville Landfill Site?

Granville Landfill Site has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Granville Landfill Site?

REPD records the operator as Biogas Technology Ltd/Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Granville Landfill Site approved and built?

The application was submitted on 30 April 1994. Permission was granted on 1 July 1994, 2 months later. The site became operational on 1 October 1999, 63 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 562.