Renewable sites › Granville Road Solar Farm
Granville Road Solar Farm
Granville Road Solar Farm is operational in Telford and Wrekin with a recorded capacity of 5 MW, and has been generating since 2016-10-24.
Planning and build timeline
| Application submitted | 2015-09-07 |
| Permission granted | 2015-12-11 3 months after submission |
| Operational | 2016-10-24 10 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Telford and Wrekin’s record on solar
Telford and Wrekin has decided 23 solar farms and approved 100%, taking a median of 2.3 months. See every solar farm decision in Telford and Wrekin →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Granville Landfill Site Landfill Gas · Operational | 1.4 | 0.5 km |
Lyreco - Telford Distribution Centre Solar Photovoltaics · Operational | 3.8 | 0.7 km |
Sheriffhales Solar Farm Solar Photovoltaics · Operational | 8.2 | 2.9 km |
Ricoh UK Products Solar Photovoltaics · Operational | 1.2 | 3 km |
Twitch Hill, Cheswell Grange Farm - Solar Farm & Battery Storage Battery · Under Construction | — | 4.2 km |
Twitch Hill, Cheswell Grange Farm - Solar Farm & Battery Storage Solar Photovoltaics · Under Construction | 25 | 4.2 km |
Wheat Leasows Solar Park Solar Photovoltaics · Operational | 4 | 5.2 km |
Steeraway Farm - Solar Farm Solar Photovoltaics · Under Construction | 30 | 7.3 km |
How big is Granville Road Solar Farm?
Granville Road Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Granville Road Solar Farm?
REPD records the operator as Solstice Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Granville Road Solar Farm approved and built?
The application was submitted on 2015-09-07. Permission was granted on 2015-12-11, 3 months later. The site became operational on 2016-10-24, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5670.