Great Eppleton Farm Repowering is an operational 8.2 MW onshore wind farm in Sunderland, generating since 1 March 2010. Planning permission was granted on 10 August 2007, 5 months after submission. Operator of record: E.ON UK.
Planning and build timeline
| Application submitted | 1 March 2007 |
| Permission granted | 10 August 2007 5 months after submission |
| Operational | 1 March 2010 31 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Sunderland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Great Eppleton Farm Repowering’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 3 | 0 km |
Wind Onshore · Operational | 7.5 | 2.2 km |
Landfill Gas · Operational | 3 | 2.4 km |
Battery · Operational | 49 | 3.6 km |
Wind Onshore · Operational | 4 | 4.4 km |
Solar Photovoltaics · Under Construction | — | 5.2 km |
Landfill Gas · Operational | 1 | 5.7 km |
Wind Onshore · Operational | 2.6 | 5.9 km |
How big is Great Eppleton Farm Repowering?
Great Eppleton Farm Repowering has a recorded installed capacity of 8.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Great Eppleton Farm Repowering?
REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Great Eppleton Farm Repowering approved and built?
The application was submitted on 1 March 2007. Permission was granted on 10 August 2007, 5 months later. The site became operational on 1 March 2010, 31 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3504.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode