Novarly ParcelRenewable sites

Renewable sitesGreat Eppleton Wind Farm

Great Eppleton Wind Farm

Great Eppleton Wind Farm is operational in Sunderland with a recorded capacity of 3 MW, and has been generating since 1997-04-01.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 1997-04-01
Wind Onshore
Technology
Border Windfarm Limited / AMEC
Sunderland
Authority
England

Planning and build timeline

Application submitted1995-08-02
Permission granted1996-07-25
12 months after submission
Operational1997-04-01
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Great Eppleton Farm Repowering
Wind Onshore · Operational
8.20 km
South Sharpley Wind Farm (Revised)
Wind Onshore · Operational
7.52.2 km
Houghton-le-Spring Landfill Site
Landfill Gas · Operational
32.4 km
Hawthorn Grid Site - Battery Storage
Battery · Operational
493.6 km
High Haswell Wind Farm
Wind Onshore · Operational
44.4 km
Sedgeletch Sewage Treatment Works
Solar Photovoltaics · Under Construction
5.2 km
Mark's Quarry
Landfill Gas · Operational
15.7 km
High Sharpley Wind Farm
Wind Onshore · Operational
2.65.9 km

How big is Great Eppleton Wind Farm?

Great Eppleton Wind Farm has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Great Eppleton Wind Farm?

REPD records the operator as Border Windfarm Limited / AMEC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Great Eppleton Wind Farm approved and built?

The application was submitted on 1995-08-02. Permission was granted on 1996-07-25, 12 months later. The site became operational on 1997-04-01, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2591.