Novarly ParcelRenewable sites

Renewable sitesGreat Eppleton Wind Farm

Great Eppleton Wind Farm

Great Eppleton Wind Farm is an operational 3 MW onshore wind farm in Sunderland, generating since 1 April 1997. Planning permission was granted on 25 July 1996, 12 months after submission. Operator of record: Border Windfarm Limited / AMEC.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 1997
Wind Onshore
Technology
Border Windfarm Limited / AMEC
Sunderland
Authority
England

Planning and build timeline

Application submitted2 August 1995
Permission granted25 July 1996
12 months after submission
Operational1 April 1997
8 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Sunderland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Great Eppleton Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
8.20 km
Wind Onshore · Operational
7.52.2 km
Landfill Gas · Operational
32.4 km
Battery · Operational
493.6 km
Wind Onshore · Operational
44.4 km
Solar Photovoltaics · Under Construction
5.2 km
Landfill Gas · Operational
15.7 km
Wind Onshore · Operational
2.65.9 km

How big is Great Eppleton Wind Farm?

Great Eppleton Wind Farm has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Great Eppleton Wind Farm?

REPD records the operator as Border Windfarm Limited / AMEC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Great Eppleton Wind Farm approved and built?

The application was submitted on 2 August 1995. Permission was granted on 25 July 1996, 12 months later. The site became operational on 1 April 1997, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2591.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode