Renewable sites › Grange Farm (Cornwall)
Grange Farm (Cornwall)
Grange Farm (Cornwall) is an operational 5 MW solar farm in Cornwall, generating since 28 February 2013. Planning permission was granted on 24 May 2011, 3 months after submission. Operator of record: Vogt Solar.
Planning and build timeline
| Application submitted | 4 March 2011 |
| Permission granted | 24 May 2011 3 months after submission |
| Operational | 28 February 2013 21 months after consent |
Screening a site of your own?
Cornwall approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Grange Farm (Cornwall)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on solar
Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 6.8 | 1.8 km |
Solar Photovoltaics · Operational | 5 | 1.9 km |
Solar Photovoltaics · Operational | 5 | 2.3 km |
Solar Photovoltaics · Operational | 41 | 4.8 km |
Solar Photovoltaics · Operational | 5 | 4.8 km |
Wind Onshore · Operational | 1.5 | 7.2 km |
Solar Photovoltaics · Operational | 5.3 | 7.9 km |
Solar Photovoltaics · Operational | 42 | 8.9 km |
How big is Grange Farm (Cornwall)?
Grange Farm (Cornwall) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Grange Farm (Cornwall)?
REPD records the operator as Vogt Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Grange Farm (Cornwall) approved and built?
The application was submitted on 4 March 2011. Permission was granted on 24 May 2011, 3 months later. The site became operational on 28 February 2013, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1572.
Novarly Parcel · official public data, read properly · parcel.novarly.com