Lower End Farm

Lower End Farm is operational in Wiltshire with a recorded capacity of 4.9 MW, and has been generating since 2015-06-30.

4.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-06-30
Solar Photovoltaics
Technology
Good Energy Generation
Wiltshire
Authority
England

Planning and build timeline

Application submitted2014-03-12
Permission granted2014-08-26
5 months after submission
Operational2015-06-30
10 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on solar

Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Stokes Marsh Farm
Solar Photovoltaics · Operational
16.63.2 km
CRAYSMARSH SOLAR FARM
Solar Photovoltaics · Operational
1.87.4 km
Snarlton Farm (Melksham solar farm)
Solar Photovoltaics · Operational
49.68.2 km
Land north of Ashton Road
Solar Photovoltaics · Operational
48.3 km
Hopton Road Industrial Estate
Solar Photovoltaics · Operational
1.38.7 km
Westbury (Closed) Landfill Site
Solar Photovoltaics · Operational
3.59.3 km
Bromham House Farm
Anaerobic Digestion · Operational
1.59.5 km
Westbury Landfill Scheme
Landfill Gas · Operational
1.19.9 km

How big is Lower End Farm?

Lower End Farm has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lower End Farm?

REPD records the operator as Good Energy Generation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lower End Farm approved and built?

The application was submitted on 2014-03-12. Permission was granted on 2014-08-26, 5 months later. The site became operational on 2015-06-30, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2159.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council