Renewable sites › Stokes Marsh Farm
Stokes Marsh Farm
Stokes Marsh Farm is operational in Wiltshire with a recorded capacity of 16.6 MW, and has been generating since 2015-03-12.
Planning and build timeline
| Application submitted | 2013-08-01 |
| Permission granted | 2013-12-18 5 months after submission |
| Operational | 2015-03-12 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Wiltshire’s record on solar
Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lower End Farm Solar Photovoltaics · Operational | 4.9 | 3.2 km |
Land north of Ashton Road Solar Photovoltaics · Operational | 4 | 5.2 km |
CRAYSMARSH SOLAR FARM Solar Photovoltaics · Operational | 1.8 | 6.2 km |
Westbury (Closed) Landfill Site Solar Photovoltaics · Operational | 3.5 | 6.6 km |
Westbury Landfill Scheme Landfill Gas · Operational | 1.1 | 7.2 km |
Snarlton Farm (Melksham solar farm) Solar Photovoltaics · Operational | 49.6 | 7.3 km |
Marsh Farm Hilperton Solar Photovoltaics · Operational | 9.1 | 8 km |
Blenches Mill Solar Photovoltaics · Operational | 6.1 | 8.2 km |
How big is Stokes Marsh Farm?
Stokes Marsh Farm has a recorded installed capacity of 16.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Stokes Marsh Farm?
REPD records the operator as South West Solar Parks. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Stokes Marsh Farm approved and built?
The application was submitted on 2013-08-01. Permission was granted on 2013-12-18, 5 months later. The site became operational on 2015-03-12, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2358.