Loftsome Bridge is operational in East Riding of Yorkshire with a recorded capacity of 1.3 MW, and has been generating since 2008-02-01.

1.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2008-02-01
Wind Onshore
Technology
Yorkshire Water
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted2006-06-28
Permission granted2007-01-31
7 months after submission
Operational2008-02-01
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on onshore wind

East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Rusholme Grange
Battery · Operational
402.9 km
Rusholme Wind Farm
Wind Onshore · Operational
243 km
Drax Biomass Power Station - Unit 2
Biomass (dedicated) · Operational
6454.2 km
Drax Biomass Power Station - Unit 1
Biomass (co-firing) · Operational
6454.2 km
Drax Biomass Power Station - Unit 3
Biomass (dedicated) · Operational
6454.2 km
Drax Biomass Power Station - Unit 4
Biomass (dedicated) · Operational
6454.2 km
Whitemoor
Biomass (dedicated) · Operational
187.4 km
Sixpenny Wood Windfarm
Wind Onshore · Operational
338.6 km

How big is Loftsome Bridge?

Loftsome Bridge has a recorded installed capacity of 1.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Loftsome Bridge?

REPD records the operator as Yorkshire Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Loftsome Bridge approved and built?

The application was submitted on 2006-06-28. Permission was granted on 2007-01-31, 7 months later. The site became operational on 2008-02-01, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2943.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council