Rusholme Wind Farm
Rusholme Wind Farm is operational in North Yorkshire with a recorded capacity of 24 MW, and has been generating since 2010-10-04.
Planning and build timeline
| Application submitted | 2004-07-02 |
| Permission granted | 2006-10-16 27 months after submission |
| Operational | 2010-10-04 48 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Yorkshire’s record on onshore wind
North Yorkshire has decided 18 onshore wind schemes and approved 72%, taking a median of 5.8 months. See every onshore wind scheme decision in North Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rusholme Grange Battery · Operational | 40 | 0.7 km |
Drax Biomass Power Station - Unit 2 Biomass (dedicated) · Operational | 645 | 2.9 km |
Drax Biomass Power Station - Unit 4 Biomass (dedicated) · Operational | 645 | 2.9 km |
Drax Biomass Power Station - Unit 1 Biomass (co-firing) · Operational | 645 | 2.9 km |
Drax Biomass Power Station - Unit 3 Biomass (dedicated) · Operational | 645 | 2.9 km |
Loftsome Bridge Wind Onshore · Operational | 1.3 | 3 km |
Croda Chemicals Europe Wind Onshore · Operational | 3 | 6.6 km |
Goole Fields ll Wind Farm Wind Onshore · Operational | 34.9 | 7.2 km |
How big is Rusholme Wind Farm?
Rusholme Wind Farm has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rusholme Wind Farm?
REPD records the operator as EDF/China General Nuclear Power Corporation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rusholme Wind Farm approved and built?
The application was submitted on 2004-07-02. Permission was granted on 2006-10-16, 27 months later. The site became operational on 2010-10-04, 48 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3602.