Rusholme Grange
Rusholme Grange is an operational 40 MW battery storage site in North Yorkshire, generating since 1 August 2024. Planning permission was granted on 3 September 2021, 3 months after submission. Operator of record: Harmony Energy Storage.
Planning and build timeline
| Application submitted | 26 May 2021 |
| Permission granted | 3 September 2021 3 months after submission |
| Operational | 1 August 2024 35 months after consent |
Screening a site of your own?
North Yorkshire approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Rusholme Grange’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Yorkshire’s record on battery storage
North Yorkshire has decided 29 battery storage schemes and approved 100%, taking a median of 10.5 months. See every battery storage scheme decision in North Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 24 | 0.7 km |
Wind Onshore · Operational | 1.3 | 2.9 km |
Biomass (dedicated) · Operational | 645 | 3.6 km |
Biomass (dedicated) · Operational | 645 | 3.6 km |
Biomass (co-firing) · Operational | 645 | 3.6 km |
Biomass (dedicated) · Operational | 645 | 3.6 km |
Wind Onshore · Operational | 34.9 | 6.9 km |
Wind Onshore · Operational | 3 | 7.1 km |
How big is Rusholme Grange?
Rusholme Grange has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rusholme Grange?
REPD records the operator as Harmony Energy Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rusholme Grange approved and built?
The application was submitted on 26 May 2021. Permission was granted on 3 September 2021, 3 months later. The site became operational on 1 August 2024, 35 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9121.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode