Renewable sites › Grain Harvesters Ltd
Grain Harvesters Ltd
Grain Harvesters Ltd is operational in Dover with a recorded capacity of 1 MW, and has been generating since 2014-12-01.
Planning and build timeline
| Application submitted | 2013-12-05 |
| Permission granted | 2014-03-06 3 months after submission |
| Operational | 2014-12-01 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dover’s record on solar
Dover has decided 16 solar farms and approved 88%, taking a median of 3.7 months. See every solar farm decision in Dover →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Home Farm (Knowlton - solar) Solar Photovoltaics · Operational | 11.5 | 4.3 km |
Marshborough Farm solar park Solar Photovoltaics · Operational | 5 | 5.4 km |
Littlebourne Solar Photovoltaics · Operational | 17 | 6.1 km |
Tilmanstone Colliery Solar Photovoltaics · Operational | 10 | 7.1 km |
Discovery Park Biomass (dedicated) · Operational | 16 | 8.2 km |
Ebbsfleet Solar Farm Solar Photovoltaics · Operational | 5 | 9 km |
Richborough Energy Park Battery · Operational | 49.9 | 9.3 km |
Richborough Energy Park - Phase 2 Battery · Operational | 50.1 | 9.3 km |
How big is Grain Harvesters Ltd?
Grain Harvesters Ltd has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Grain Harvesters Ltd?
REPD records the operator as Grain Harvesters Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Grain Harvesters Ltd approved and built?
The application was submitted on 2013-12-05. Permission was granted on 2014-03-06, 3 months later. The site became operational on 2014-12-01, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1320.
Novarly Parcel · official public data, read properly · parcel.novarly.com