Renewable sitesJG Pears' animal rendering facility

JG Pears' animal rendering facility

JG Pears' animal rendering facility is operational in Bassetlaw with a recorded capacity of 12 MW, and has been generating since 2018-04-15.

12 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-04-15
Biomass (dedicated)
Technology
JG Pears Power
Bassetlaw
Authority
England

Planning and build timeline

Application submitted2011-12-23
Permission granted2014-10-22
34 months after submission
Operational2018-04-15
42 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Egmanton Solar Farm
Solar Photovoltaics · Operational
14.25.5 km
Westwood Farm Solar Park
Solar Photovoltaics · Operational
5.18.6 km
Rampton Hospital Energy Centre
Biomass (dedicated) · Operational
1.28.9 km
Lincoln Landfill Scheme
Landfill Gas · Operational
212.7 km
Walmoor Farm solar park
Solar Photovoltaics · Operational
412.8 km
Lincoln EFW
EfW Incineration · Operational
16.412.9 km
Danes Farm
Solar Photovoltaics · Operational
3.313.8 km
Danes Farm - extension
Solar Photovoltaics · Operational
10.513.8 km

How big is JG Pears' animal rendering facility?

JG Pears' animal rendering facility has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates JG Pears' animal rendering facility?

REPD records the operator as JG Pears Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was JG Pears' animal rendering facility approved and built?

The application was submitted on 2011-12-23. Permission was granted on 2014-10-22, 34 months later. The site became operational on 2018-04-15, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6227.