Renewable sites › JG Pears' animal rendering facility
JG Pears' animal rendering facility
JG Pears' animal rendering facility is operational in Bassetlaw with a recorded capacity of 12 MW, and has been generating since 2018-04-15.
Planning and build timeline
| Application submitted | 2011-12-23 |
| Permission granted | 2014-10-22 34 months after submission |
| Operational | 2018-04-15 42 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Egmanton Solar Farm Solar Photovoltaics · Operational | 14.2 | 5.5 km |
Westwood Farm Solar Park Solar Photovoltaics · Operational | 5.1 | 8.6 km |
Rampton Hospital Energy Centre Biomass (dedicated) · Operational | 1.2 | 8.9 km |
Lincoln Landfill Scheme Landfill Gas · Operational | 2 | 12.7 km |
Walmoor Farm solar park Solar Photovoltaics · Operational | 4 | 12.8 km |
Lincoln EFW EfW Incineration · Operational | 16.4 | 12.9 km |
Danes Farm Solar Photovoltaics · Operational | 3.3 | 13.8 km |
Danes Farm - extension Solar Photovoltaics · Operational | 10.5 | 13.8 km |
How big is JG Pears' animal rendering facility?
JG Pears' animal rendering facility has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates JG Pears' animal rendering facility?
REPD records the operator as JG Pears Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was JG Pears' animal rendering facility approved and built?
The application was submitted on 2011-12-23. Permission was granted on 2014-10-22, 34 months later. The site became operational on 2018-04-15, 42 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6227.