Renewable sites › Leverton Farm - Energy Barn
Leverton Farm - Energy Barn
Leverton Farm - Energy Barn is an operational 10 MW battery storage site in West Lindsey, generating since 1 January 2018. REPD does not record the planning grant date. Operator of record: Eelpower.
Planning and build timeline
| Application submitted | 4 July 2014 |
| Permission granted | not recorded |
| Operational | 1 January 2018 |
Screening a site of your own?
Redline runs the record on your own boundary in West Lindsey: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Leverton Farm - Energy Barn’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Conservation area — Burton
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
EfW Incineration · Operational | 16.4 | 7.3 km |
Landfill Gas · Operational | 2 | 7.6 km |
Anaerobic Digestion · Operational | 1.1 | 8.7 km |
Solar Photovoltaics · Operational | 22 | 9.2 km |
Solar Photovoltaics · Operational | 12 | 9.2 km |
Solar Photovoltaics · Operational | 18.9 | 10.6 km |
Solar Photovoltaics · Under Construction | 40 | 10.7 km |
Solar Photovoltaics · Operational | 3.3 | 11.3 km |
How big is Leverton Farm - Energy Barn?
Leverton Farm - Energy Barn has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Leverton Farm - Energy Barn?
REPD records the operator as Eelpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Leverton Farm - Energy Barn approved and built?
The application was submitted on 4 July 2014. REPD does not record a grant date. The site became operational on 1 January 2018.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6917.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode