Land to the south of Hill Farm
Land to the south of Hill Farm is operational in West Northamptonshire with a recorded capacity of 6.8 MW, and has been generating since 2017-03-31.
Planning and build timeline
| Application submitted | 2015-10-22 |
| Permission granted | 2016-01-14 3 months after submission |
| Operational | 2017-03-31 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
West Northamptonshire’s record on solar
West Northamptonshire has decided 61 solar farms and approved 92%, taking a median of 2.9 months. See every solar farm decision in West Northamptonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Nectar Way Regional Distribution Centre Solar Photovoltaics · Operational | 1 | 1.9 km |
Weston Landfill Site Landfill Gas · Operational | 2 | 3.5 km |
Cinch Stadium, Franklin�s Gardens - Solar Solar Photovoltaics · Operational | 8.8 | 5.5 km |
Land South of Knock Lane Solar Photovoltaics · Operational | 4 | 6 km |
Wooton Landfill Gas · Operational | 2 | 6.3 km |
Northampton General Hospital Biomass (dedicated) · Operational | 1.9 | 7.3 km |
Wieland Nemco, Pennard Close - Solar panels Solar Photovoltaics · Operational | 0.15 | 7.8 km |
East Lodge Farm, Quinton Road - Anaerobic Digestion Facility Anaerobic Digestion · Under Construction | — | 8.2 km |
How big is Land to the south of Hill Farm?
Land to the south of Hill Farm has a recorded installed capacity of 6.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land to the south of Hill Farm?
REPD records the operator as TGC Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land to the south of Hill Farm approved and built?
The application was submitted on 2015-10-22. Permission was granted on 2016-01-14, 3 months later. The site became operational on 2017-03-31, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5880.