Cinch Stadium, Franklin�s Gardens - Solar is an operational 8.8 MW solar farm in West Northamptonshire, generating since 20 May 2022. REPD does not record the planning grant date. Operator of record: Solivus.
Planning and build timeline
| Application submitted | not recorded |
| Permission granted | not recorded |
| Operational | 20 May 2022 |
Screening a site of your own?
West Northamptonshire approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Cinch Stadium, Franklin�s Gardens - Solar’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
West Northamptonshire’s record on solar
West Northamptonshire has decided 61 solar farms and approved 92%, taking a median of 2.9 months. See every solar farm decision in West Northamptonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Biomass (dedicated) · Operational | 1.9 | 2.6 km |
Solar Photovoltaics · Operational | 1 | 3.7 km |
Solar Photovoltaics · Operational | 0.15 | 4.3 km |
Solar Photovoltaics · Operational | 6.8 | 5.5 km |
Landfill Gas · Operational | 2 | 5.8 km |
Landfill Gas · Operational | 2 | 7.1 km |
Anaerobic Digestion · Under Construction | — | 8.6 km |
Solar Photovoltaics · Operational | 4 | 8.6 km |
How big is Cinch Stadium, Franklin�s Gardens - Solar?
Cinch Stadium, Franklin�s Gardens - Solar has a recorded installed capacity of 8.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cinch Stadium, Franklin�s Gardens - Solar?
REPD records the operator as Solivus. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cinch Stadium, Franklin�s Gardens - Solar approved and built?
REPD does not record a submission date. REPD does not record a grant date. The site became operational on 20 May 2022.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11330.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode