East Lodge Farm, Quinton Road - Anaerobic Digestion Facility

East Lodge Farm, Quinton Road - Anaerobic Digestion Facility is under construction in West Northamptonshire.

Capacity
as recorded in REPD
Under Construction
Status
no operational date
Anaerobic Digestion
Technology
Acorn Bioenergy Limited
West Northamptonshire
Authority
England

Planning and build timeline

Application submitted2023-02-13
Permission granted2024-01-18
11 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
M1 Wind Farm
Wind Onshore · Operational
7.21.2 km
Wooton
Landfill Gas · Operational
22.8 km
Land South of Knock Lane
Solar Photovoltaics · Operational
43.4 km
Stonepit Farm
Solar Photovoltaics · Operational
54.3 km
Bulls Head Farm North
Solar Photovoltaics · Operational
4.74.6 km
Salcey Solar Farm
Battery · Operational
15 km
Wieland Nemco, Pennard Close - Solar panels
Solar Photovoltaics · Operational
0.155.8 km
Manor Farm (Horton)
Solar Photovoltaics · Operational
56.4 km

How big is East Lodge Farm, Quinton Road - Anaerobic Digestion Facility?

REPD does not record an installed capacity for East Lodge Farm, Quinton Road - Anaerobic Digestion Facility.

Who operates East Lodge Farm, Quinton Road - Anaerobic Digestion Facility?

REPD records the operator as Acorn Bioenergy Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was East Lodge Farm, Quinton Road - Anaerobic Digestion Facility approved and built?

The application was submitted on 2023-02-13. Permission was granted on 2024-01-18, 11 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12268.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council