Renewable sites › Wooton
Wooton
Wooton is operational in West Northamptonshire with a recorded capacity of 2 MW, and has been generating since 2003-07-04.
Planning and build timeline
| Application submitted | 2001-12-14 |
| Permission granted | 2002-12-13 12 months after submission |
| Operational | 2003-07-04 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
East Lodge Farm, Quinton Road - Anaerobic Digestion Facility Anaerobic Digestion · Under Construction | — | 2.8 km |
Wieland Nemco, Pennard Close - Solar panels Solar Photovoltaics · Operational | 0.15 | 3.5 km |
M1 Wind Farm Wind Onshore · Operational | 7.2 | 3.9 km |
Land South of Knock Lane Solar Photovoltaics · Operational | 4 | 4 km |
Northampton General Hospital Biomass (dedicated) · Operational | 1.9 | 4.9 km |
Cinch Stadium, Franklin�s Gardens - Solar Solar Photovoltaics · Operational | 8.8 | 5.8 km |
Nectar Way Regional Distribution Centre Solar Photovoltaics · Operational | 1 | 5.9 km |
Land to the south of Hill Farm Solar Photovoltaics · Operational | 6.8 | 6.3 km |
How big is Wooton?
Wooton has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wooton?
REPD records the operator as Viridor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wooton approved and built?
The application was submitted on 2001-12-14. Permission was granted on 2002-12-13, 12 months later. The site became operational on 2003-07-04, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 646.