Land East of White Horse Lane is an operational 5 MW solar farm in South Norfolk, generating since 30 March 2016. Planning permission was granted on 11 August 2015, 8 months after submission. Operator of record: Island Green Power.
Planning and build timeline
| Application submitted | 9 December 2014 |
| Permission granted | 11 August 2015 8 months after submission |
| Operational | 30 March 2016 8 months after consent |
Screening a site of your own?
South Norfolk approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land East of White Horse Lane’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Nutrient-neutrality catchment — Yare Broads and Marshes
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Norfolk’s record on solar
South Norfolk has decided 28 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in South Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1.9 | 5.5 km |
Solar Photovoltaics · Operational | 7.3 | 6.5 km |
Solar Photovoltaics · Operational | 5 | 7 km |
Solar Photovoltaics · Under Construction | 28.5 | 8 km |
Battery · Under Construction | — | 8.1 km |
Solar Photovoltaics · Under Construction | 5 | 8.2 km |
Landfill Gas · Operational | 2 | 9.2 km |
Battery · Operational | 0.1 | 9.8 km |
How big is Land East of White Horse Lane?
Land East of White Horse Lane has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land East of White Horse Lane?
REPD records the operator as Island Green Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land East of White Horse Lane approved and built?
The application was submitted on 9 December 2014. Permission was granted on 11 August 2015, 8 months later. The site became operational on 30 March 2016, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4885.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode