Costessey Landfill Gas Project 2

Costessey Landfill Gas Project 2 is operational in South Norfolk with a recorded capacity of 2 MW, and has been generating since 2003-05-14.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2003-05-14
Landfill Gas
Technology
Combined Landfill Projects (CLP)
South Norfolk
Authority
England

Planning and build timeline

Application submitted2002-05-21
Permission granted2002-09-27
4 months after submission
Operational2003-05-14
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
New Road Solar Farm
Solar Photovoltaics · Under Construction
51.5 km
Briar Solar Farm
Solar Photovoltaics · Operational
1.94.4 km
Attlebridge Landfill Site
Landfill Gas · Operational
1.35.5 km
Reepham Road (Waste AD)
Anaerobic Digestion · Operational
1.55.5 km
Spring Farm (biomass)
Anaerobic Digestion · Operational
15.6 km
Colton - Solar photovoltaic farm, Battery storage
Solar Photovoltaics · Under Construction
307.1 km
Colton - Solar photovoltaic farm, Battery storage
Battery · Under Construction
307.1 km
The Old Airfield
Solar Photovoltaics · Operational
57.6 km

How big is Costessey Landfill Gas Project 2?

Costessey Landfill Gas Project 2 has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Costessey Landfill Gas Project 2?

REPD records the operator as Combined Landfill Projects (CLP). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Costessey Landfill Gas Project 2 approved and built?

The application was submitted on 2002-05-21. Permission was granted on 2002-09-27, 4 months later. The site became operational on 2003-05-14, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 733.