Costessey Landfill Gas Project 2
Costessey Landfill Gas Project 2 is operational in South Norfolk with a recorded capacity of 2 MW, and has been generating since 2003-05-14.
Planning and build timeline
| Application submitted | 2002-05-21 |
| Permission granted | 2002-09-27 4 months after submission |
| Operational | 2003-05-14 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
- Nutrient-neutrality catchment — Yare Broads and Marshes
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
New Road Solar Farm Solar Photovoltaics · Under Construction | 5 | 1.5 km |
Briar Solar Farm Solar Photovoltaics · Operational | 1.9 | 4.4 km |
Attlebridge Landfill Site Landfill Gas · Operational | 1.3 | 5.5 km |
Reepham Road (Waste AD) Anaerobic Digestion · Operational | 1.5 | 5.5 km |
Spring Farm (biomass) Anaerobic Digestion · Operational | 1 | 5.6 km |
Colton - Solar photovoltaic farm, Battery storage Solar Photovoltaics · Under Construction | 30 | 7.1 km |
Colton - Solar photovoltaic farm, Battery storage Battery · Under Construction | 30 | 7.1 km |
The Old Airfield Solar Photovoltaics · Operational | 5 | 7.6 km |
How big is Costessey Landfill Gas Project 2?
Costessey Landfill Gas Project 2 has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Costessey Landfill Gas Project 2?
REPD records the operator as Combined Landfill Projects (CLP). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Costessey Landfill Gas Project 2 approved and built?
The application was submitted on 2002-05-21. Permission was granted on 2002-09-27, 4 months later. The site became operational on 2003-05-14, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 733.