Avenue Farm
Avenue Farm is operational in South Norfolk with a recorded capacity of 7.3 MW, and has been generating since 2015-03-20.
Planning and build timeline
| Application submitted | 2014-03-04 |
| Permission granted | 2014-10-31 8 months after submission |
| Operational | 2015-03-20 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Norfolk’s record on solar
South Norfolk has decided 28 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in South Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land East of White Horse Lane Solar Photovoltaics · Operational | 5 | 6.5 km |
Land south of Brick Kiln Road Solar Photovoltaics · Operational | 5 | 9.8 km |
Hall Farm Solar park Solar Photovoltaics · Operational | 15 | 10.2 km |
Briar Solar Farm Solar Photovoltaics · Operational | 1.9 | 11.8 km |
Bracon Ash Solar Solar Photovoltaics · Under Construction | 28.5 | 12.1 km |
Bracon Ash Solar Battery · Under Construction | — | 12.2 km |
Salhouse Solar Farm Solar Photovoltaics · Operational | 5 | 12.6 km |
The Everest System Battery · Operational | 0.1 | 14.3 km |
How big is Avenue Farm?
Avenue Farm has a recorded installed capacity of 7.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Avenue Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Avenue Farm approved and built?
The application was submitted on 2014-03-04. Permission was granted on 2014-10-31, 8 months later. The site became operational on 2015-03-20, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1909.