Land at Hill Farm

Land at Hill Farm is an operational 1.2 MW solar farm in North West Leicestershire, generating since 1 November 2016. Planning permission was granted on 12 October 2015, 3 months after submission. Operator of record: Hill Farm.

1.2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 November 2016
Solar Photovoltaics
Technology
Hill Farm
North West Leicestershire
Authority
England

Planning and build timeline

Application submitted23 July 2015
Permission granted12 October 2015
3 months after submission
Operational1 November 2016
13 months after consent

Screening a site of your own?

RedlineUK · £39

North West Leicestershire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land at Hill Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North West Leicestershire’s record on solar

North West Leicestershire has decided 28 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North West Leicestershire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.30.7 km
Battery · Operational
100.9 km
Solar Photovoltaics · Operational
13.92.7 km
Solar Photovoltaics · Operational
52.7 km
Solar Photovoltaics · Operational
2.83.5 km
Landfill Gas · Operational
1.14.5 km
Solar Photovoltaics · Operational
34.6 km
Solar Photovoltaics · Operational
165.1 km

How big is Land at Hill Farm?

Land at Hill Farm has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Hill Farm?

REPD records the operator as Hill Farm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Hill Farm approved and built?

The application was submitted on 23 July 2015. Permission was granted on 12 October 2015, 3 months later. The site became operational on 1 November 2016, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5530.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode