Novarly ParcelRenewable planning

Renewable planning SolarNorth West Leicestershire

Solar planning in North West Leicestershire

North West Leicestershire has decided 28 solar farms and approved 96% of them, taking a median of 2.7 months to decide. Consented capacity: 90 MW. 6 applications still awaiting a decision.

96%
Approved
27 granted · 1 refused
2.7 mo
Median decision
UK 2.3 mo
90 MW
Consented
5 MW refused
0
Appeals
no appeals recorded

How North West Leicestershire compares

Against the 298 UK authorities with 5+ solar decisions, North West Leicestershire sits in the 47th percentile for approval rate (3 points above the England average) and the 42nd percentile for speed.

Decisions by year

35Approved — 1 (2011)111Approved — 5 (2014)514Approved — 5 (2015)515Refused — 1 (2016)116Approved — 1 (2018)118Approved — 2 (2021)221Approved — 2 (2022)222Approved — 3 (2023)323Approved — 5 (2024)524Approved — 2 (2025)225
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (37)

SchemeMWStatusDecided
Clinitron House, Excelsior Road - Solar Panels
RR UK (South) Limited · 26/00359/PNM
0.16Application Submitted2026-03-16
Mediq House, Arundel Avenue - Solar Panels
Private Developer · 25/01530/PNM
0.45Application Submitted2025-10-31
Plot 3a, Emdc Arundel Avenue - Solar Panels
Ineco Energy Limited · 25/01533/PNM
0.16Application Submitted2025-10-31
Moto Donington Park - Solar Farm
Dunkin Rushton Limited / Moto Hospitality Limited · 23/01712/FULM · 15.6 mo to decide
Awaiting Construction2025-05-12
Whitwick And Coalville Leisure Centre, Stephenson Way - Solar Panels
Whitwick And Coalville Leisure Centre · 24/01568/PNM · 1.8 mo to decide
0.35Awaiting Construction2025-02-06
Ceva House, Excelsior Road - Solar Panels
CEVA Logistics · 25/00220/PNM
0.22Application Submitted2025-02-04
Ceva House, Excelsior Road - Solar Panels
CEVA Logistics · 24/01493/PNM · 1.8 mo to decide
0.22Revised2025-01-17
DSV, Stretton En Le Field - Solar Panels
DSV · 24/01073/PNM · 1.2 mo to decide
0.21Awaiting Construction2024-10-16
Bardon Quarry - Solar Panels
Regenerco Limited · 24/00830/PNM · 1.8 mo to decide
0.19Awaiting Construction2024-08-29
Mushroom Farm, Lower Fields - Agricultural Building & Solar Panels
Livesey Brothers · 23/01643/FULM · 6.9 mo to decide
0.58Awaiting Construction2024-07-04
East Midlands Distribution Centre, Arundel Avenue - Solar Panels
Buy It Direct Limited · 24/00301/PNM · 2.7 mo to decide
0.32Awaiting Construction2024-05-21
Motability Operations Limited, Stephenson Court - Solar Panels
Motability Operations Limited · 24/00285/PNM · 1.8 mo to decide
0.28Awaiting Construction2024-04-22
Charley Road - Solar Farm
Namene Solar · P/23/2029/2
49.9Application Submitted2023-11-22
Park Farmhouse Hotel, Castle Donington - Solar Panels
Park Farmhouse Hotel · 23/00356/FUL · 5.2 mo to decide
Awaiting Construction2023-08-24
Gateway House, Interlink Way West - Solar Panels
Logicor · 23/00581/PNM · 1.6 mo to decide
0.57Awaiting Construction2023-06-28
Mercia Park, Burton Road - Solar PV Panels
DSV · 23/00126/PNM · 1.5 mo to decide
1Awaiting Construction2023-03-21
Unit 3, Wilders Way - Solar Photovoltaic Panels
The Very Group · 21/00422/FULM · 18.4 mo to decide
4.2Awaiting Construction2022-09-20
Morrisons, Whitwick Road - Solar Panels
WM Morrisons Supermarkets Plc · 22/00234/PNM · 2 mo to decide
0.75Awaiting Construction2022-04-11
West Lane, Bardon Hill - Solar PV System
BeBa Energy UK Limited · 21/01066/PNM · 2.1 mo to decide
0.61Awaiting Construction2021-08-04
Lower Fields Mushroom Farm
Livesey Brothers · 20/00504/FUL · 10.4 mo to decide
0.3Operational2021-02-05
Pretoria Road
Lightsource BP · 18/01595/FULM · 2.8 mo to decide
4.9Operational2018-12-21
Amazon - BHX2
Amazon UK Services / Push Energy · 18/01437/FULM
3.7Planning Permission Expired2018-08-29
Lane East of Drakelow Road
TW Solar · 9/2015/0858 · 5.4 mo to decide
5Application Refused2016-03-04
Land at Hill Farm
Hill Farm · 15/00719/FULM · 2.7 mo to decide
1.2Operational2015-10-12
Land at Ingles Hill Farm
Sunventures (Suncredit UK) · 15/00714/FULM · 2.2 mo to decide
3Operational2015-09-29
United Biscuits Distribution Warehouse
Lightsource Renewable Energy · 15/00758/PDNALO · 1.6 mo to decide
1Abandoned2015-09-17
Ashby Solar Farm (b)
Solstice Renewables · 15/00500/FULM · 3.5 mo to decide
1Abandoned2015-09-09
Ashby Solar Farm (a)
Primrose Solar · 15/00499/FULM · 3.5 mo to decide
5Operational2015-09-09
Land at Whatton Road
Push Energy · 14/00847/FULM · 6.7 mo to decide
1.5Operational2015-05-06
Lockington Solar Park
Lark Energy · 14/00488/FULM · 6.9 mo to decide
15Planning Permission Expired2015-01-14
Lount solar farm
Hadstone Energy · 14/00862/FULM · 2.7 mo to decide
2.8Operational2014-12-17
Coalville solar farm
Big 60 Million · 14/00786/FULM · 2.6 mo to decide
10Abandoned2014-11-19
Packington Solar Farm
Solstice Renewables · 14/00535/FULM · 3.8 mo to decide
13.9Operational2014-10-20
Walnut Yard (Phase 1)
Lark Energy · 14/00408/FULM · 5.1 mo to decide
1.8Operational2014-10-07
Langley Priory, Walnut Yard (Phase 2)
Lark Energy · 14/00408/FULM · 5.1 mo to decide
6.2Operational2014-10-07
Prestop Park Farm
Foresight · 14/00635/FULM · 2.7 mo to decide
16Operational2014-09-30
East Midlands Distribution Centre
Marks and Spencer plc · 11/00169/VCI · 1.3 mo to decide
6.1Operational2011-04-04

Does North West Leicestershire approve solar farms?

Yes — of the 28 solar farms North West Leicestershire has decided, 96% were approved (27 granted, 1 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in North West Leicestershire?

The median time from application to decision is 2.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has North West Leicestershire consented?

90 MW has been consented across 27 approved schemes, with 5 MW refused. A further 6 applications awaits a decision.

Other technologies in North West Leicestershire

Battery storage in North West LeicestershireOnshore wind in North West Leicestershire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.