Renewable sites › Ashby Solar Farm (a)
Ashby Solar Farm (a)
Ashby Solar Farm (a) is operational in North West Leicestershire with a recorded capacity of 5 MW, and has been generating since 2016-03-12.
Planning and build timeline
| Application submitted | 2015-05-26 |
| Permission granted | 2015-09-09 3 months after submission |
| Operational | 2016-03-12 6 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Nutrient-neutrality catchment — River Mease SAC
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North West Leicestershire’s record on solar
North West Leicestershire has decided 28 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North West Leicestershire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hill Farm - Energy Barn Battery · Operational | 10 | 1.9 km |
Packington Solar Farm Solar Photovoltaics · Operational | 13.9 | 1.9 km |
Lower Fields Mushroom Farm Solar Photovoltaics · Operational | 0.3 | 2.2 km |
Land at Hill Farm Solar Photovoltaics · Operational | 1.2 | 2.7 km |
Land at Ingles Hill Farm Solar Photovoltaics · Operational | 3 | 3.8 km |
Prestop Park Farm Solar Photovoltaics · Operational | 16 | 3.9 km |
Shortheath Solar Park Solar Photovoltaics · Operational | 5 | 4.6 km |
Lount solar farm Solar Photovoltaics · Operational | 2.8 | 4.8 km |
How big is Ashby Solar Farm (a)?
Ashby Solar Farm (a) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ashby Solar Farm (a)?
REPD records the operator as Primrose Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ashby Solar Farm (a) approved and built?
The application was submitted on 2015-05-26. Permission was granted on 2015-09-09, 3 months later. The site became operational on 2016-03-12, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5273.