Hill Farm - Energy Barn

Hill Farm - Energy Barn is operational in North West Leicestershire with a recorded capacity of 10 MW, and has been generating since 2017-03-31.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-31
Battery
Technology
Anesco/ Green Hedge Energy UK
North West Leicestershire
Authority
England

Planning and build timeline

Application submitted2016-06-22
Permission grantednot recorded
Operational2017-03-31

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Land at Hill Farm
Solar Photovoltaics · Operational
1.20.9 km
Lower Fields Mushroom Farm
Solar Photovoltaics · Operational
0.31 km
Ashby Solar Farm (a)
Solar Photovoltaics · Operational
51.9 km
Packington Solar Farm
Solar Photovoltaics · Operational
13.92.5 km
Lount solar farm
Solar Photovoltaics · Operational
2.83.4 km
Land at Ingles Hill Farm
Solar Photovoltaics · Operational
33.8 km
Prestop Park Farm
Solar Photovoltaics · Operational
164.2 km
Lount/Smoile
Landfill Gas · Operational
1.14.4 km

How big is Hill Farm - Energy Barn?

Hill Farm - Energy Barn has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hill Farm - Energy Barn?

REPD records the operator as Anesco/ Green Hedge Energy UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hill Farm - Energy Barn approved and built?

The application was submitted on 2016-06-22. REPD does not record a grant date. The site became operational on 2017-03-31.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6915.