Novarly ParcelRenewable sites

Renewable sitesLount solar farm

Lount solar farm

Lount solar farm is operational in North West Leicestershire with a recorded capacity of 2.8 MW, and has been generating since 2015-11-30.

2.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-11-30
Solar Photovoltaics
Technology
Hadstone Energy
North West Leicestershire
Authority
England

Planning and build timeline

Application submitted2014-09-26
Permission granted2014-12-17
3 months after submission
Operational2015-11-30
11 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North West Leicestershire’s record on solar

North West Leicestershire has decided 28 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North West Leicestershire

Other built sites within 15 km

SiteMWDistance
Lount/Smoile
Landfill Gas · Operational
1.11 km
Land at Ingles Hill Farm
Solar Photovoltaics · Operational
33.3 km
Hill Farm - Energy Barn
Battery · Operational
103.4 km
Land at Hill Farm
Solar Photovoltaics · Operational
1.23.5 km
Prestop Park Farm
Solar Photovoltaics · Operational
164 km
Lower Fields Mushroom Farm
Solar Photovoltaics · Operational
0.34.1 km
Ashby Solar Farm (a)
Solar Photovoltaics · Operational
54.8 km
Short Hazel Solar Farm
Solar Photovoltaics · Operational
55.2 km

How big is Lount solar farm?

Lount solar farm has a recorded installed capacity of 2.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lount solar farm?

REPD records the operator as Hadstone Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lount solar farm approved and built?

The application was submitted on 2014-09-26. Permission was granted on 2014-12-17, 3 months later. The site became operational on 2015-11-30, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4841.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council