Land at Barnham is an operational 1 MW solar farm in Arun, generating since 20 February 2017. Planning permission was granted on 24 February 2016, 7 months after submission. Operator of record: Wirsol.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 20 February 2017
Solar Photovoltaics
Technology
Wirsol
Arun
Authority
England

Planning and build timeline

Application submitted10 August 2015
Permission granted24 February 2016
7 months after submission
Operational20 February 2017
12 months after consent

Screening a site of your own?

RedlineUK · £39

Arun approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land at Barnham’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Arun’s record on solar

Arun has decided 10 solar farms and approved 100%, taking a median of 3.2 months. See every solar farm decision in Arun

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
14.51.5 km
Landfill Gas · Operational
1.42.1 km
Solar Photovoltaics · Operational
52.4 km
Solar Photovoltaics · Operational
3.82.7 km
Solar Photovoltaics · Operational
63 km
Solar Photovoltaics · Operational
0.23.1 km
Solar Photovoltaics · Operational
53.4 km
Solar Photovoltaics · Operational
54.1 km

How big is Land at Barnham?

Land at Barnham has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Barnham?

REPD records the operator as Wirsol. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Barnham approved and built?

The application was submitted on 10 August 2015. Permission was granted on 24 February 2016, 7 months later. The site became operational on 20 February 2017, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5832.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode