Novarly ParcelRenewable sites

Renewable sitesBinsted Farm

Binsted Farm

Binsted Farm is operational in Arun with a recorded capacity of 5 MW, and has been generating since 2016-03-31.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-31
Solar Photovoltaics
Technology
Lightsource BP
Arun
Authority
England

Planning and build timeline

Application submitted2015-07-06
Permission granted2015-09-28
3 months after submission
Operational2016-03-31
6 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Arun’s record on solar

Arun has decided 10 solar farms and approved 100%, taking a median of 3.2 months. See every solar farm decision in Arun

Other built sites within 15 km

SiteMWDistance
Bilsham Farm
Solar Photovoltaics · Operational
14.53 km
Rookery Farm
Solar Photovoltaics · Operational
3.83.3 km
Land at Barnham
Solar Photovoltaics · Operational
13.4 km
Land at Brookbarn Farm
Solar Photovoltaics · Operational
34.6 km
Lidsey Landfill
Landfill Gas · Operational
1.45.4 km
Manor Farm - Shripney
Solar Photovoltaics · Operational
55.8 km
Decoy Farm House Solar Modules
Solar Photovoltaics · Operational
66.1 km
Tesco Superstore Shripney Road
Solar Photovoltaics · Operational
0.26.1 km

How big is Binsted Farm?

Binsted Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Binsted Farm?

REPD records the operator as Lightsource BP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Binsted Farm approved and built?

The application was submitted on 2015-07-06. Permission was granted on 2015-09-28, 3 months later. The site became operational on 2016-03-31, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6205.

Novarly Parcel · official public data, read properly · parcel.novarly.com