Renewable sites › Bilsham Farm
Bilsham Farm
Bilsham Farm is an operational 14.5 MW solar farm in Arun, generating since 10 November 2014. Planning permission was granted on 13 February 2014, 3 months after submission. Operator of record: NextEnergy Solar Fund.
Planning and build timeline
| Application submitted | 4 November 2013 |
| Permission granted | 13 February 2014 3 months after submission |
| Operational | 10 November 2014 9 months after consent |
Screening a site of your own?
Arun approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Bilsham Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Arun’s record on solar
Arun has decided 10 solar farms and approved 100%, taking a median of 3.2 months. See every solar farm decision in Arun →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 3.8 | 1.2 km |
Solar Photovoltaics · Operational | 1 | 1.5 km |
Solar Photovoltaics · Operational | 5 | 3 km |
Solar Photovoltaics · Operational | 0.2 | 3.1 km |
Solar Photovoltaics · Operational | 5 | 3.3 km |
Landfill Gas · Operational | 1.4 | 3.3 km |
Solar Photovoltaics · Operational | 6 | 4.3 km |
Solar Photovoltaics · Operational | 5 | 5.6 km |
How big is Bilsham Farm?
Bilsham Farm has a recorded installed capacity of 14.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bilsham Farm?
REPD records the operator as NextEnergy Solar Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bilsham Farm approved and built?
The application was submitted on 4 November 2013. Permission was granted on 13 February 2014, 3 months later. The site became operational on 10 November 2014, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1966.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode