Novarly ParcelRenewable sites

Renewable sitesLidsey Landfill

Lidsey Landfill

Lidsey Landfill is operational in Arun with a recorded capacity of 1.4 MW, and has been generating since 2002-06-01.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2002-06-01
Landfill Gas
Technology
LIDSEY LANDFILL LTD
Arun
Authority
England

Planning and build timeline

Application submittednot recorded
Permission granted1996-11-22
Operational2002-06-01
66 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Manor Farm - Shripney
Solar Photovoltaics · Operational
50.9 km
Decoy Farm House Solar Modules
Solar Photovoltaics · Operational
61.1 km
Land at Barnham
Solar Photovoltaics · Operational
12.1 km
Oving Solar Farm
Solar Photovoltaics · Operational
52.4 km
Tesco Superstore Shripney Road
Solar Photovoltaics · Operational
0.23 km
Park Farm
Solar Photovoltaics · Operational
53.1 km
Land at Tangmere Airfield
Solar Photovoltaics · Operational
53.2 km
Bilsham Farm
Solar Photovoltaics · Operational
14.53.3 km

How big is Lidsey Landfill?

Lidsey Landfill has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lidsey Landfill?

REPD records the operator as LIDSEY LANDFILL LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lidsey Landfill approved and built?

REPD does not record a submission date. Permission was granted on 1996-11-22. The site became operational on 2002-06-01, 66 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 596.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council