Renewable sites › Lambs Hill
Lambs Hill
Lambs Hill is operational in Stockton-on-Tees with a recorded capacity of 8 MW, and has been generating since 2017-01-19.
Planning and build timeline
| Application submitted | 2010-10-07 |
| Permission granted | 2011-12-07 14 months after submission |
| Operational | 2017-01-19 61 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Nutrient-neutrality catchment — Teesmouth and Cleveland Coast SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Eaglescliffe Solar Farm Solar Photovoltaics · Operational | 5 | 2 km |
High Meadow Farm Solar Photovoltaics · Operational | 4 | 6 km |
Billingham Chemical Works EfW Incineration · Operational | 12 | 6 km |
Teesside Green Energy Plant (Waste AD) Anaerobic Digestion · Operational | 4.8 | 6.5 km |
Albert Road Rooftop Solar Panels Solar Photovoltaics · Operational | 0.18 | 6.7 km |
Haverton Hill Incinerator EfW Incineration · Operational | 20.1 | 6.9 km |
Seamer Wind Farm - Hambleton Wind Onshore · Operational | 4 | 7 km |
Teesside EfW EfW Incineration · Operational | 19.2 | 7.1 km |
How big is Lambs Hill?
Lambs Hill has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lambs Hill?
REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lambs Hill approved and built?
The application was submitted on 2010-10-07. Permission was granted on 2011-12-07, 14 months later. The site became operational on 2017-01-19, 61 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4390.