Barlockhart Moor

Barlockhart Moor is an operational 8.1 MW onshore wind farm in Dumfries and Galloway, generating since 27 August 2013. Planning permission was granted on 26 January 2011, 29 months after submission. Operator of record: West Coast Energy.

8.1 MW
Capacity
as recorded in REPD
Operational
Status
since 27 August 2013
Wind Onshore
Technology
West Coast Energy
Dumfries and Galloway
Authority
Scotland

Planning and build timeline

Application submitted28 August 2008
Permission granted26 January 2011
29 months after submission
Operational27 August 2013
31 months after consent

Screening a site of your own?

RedlineUK · £39

Dumfries and Galloway approves 67% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Barlockhart Moor’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Dumfries and Galloway’s record on onshore wind

Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
15.33.9 km
Wind Onshore · Operational
3511 km
Wind Onshore · Operational
27.511.1 km
Wind Onshore · Operational
19.511.7 km
Wind Onshore · Operational
23913.7 km
Wind Onshore · Under Construction
50.414.6 km

How big is Barlockhart Moor?

Barlockhart Moor has a recorded installed capacity of 8.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barlockhart Moor?

REPD records the operator as West Coast Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barlockhart Moor approved and built?

The application was submitted on 28 August 2008. Permission was granted on 26 January 2011, 29 months later. The site became operational on 27 August 2013, 31 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4435.