Barlockhart Moor
Barlockhart Moor is an operational 8.1 MW onshore wind farm in Dumfries and Galloway, generating since 27 August 2013. Planning permission was granted on 26 January 2011, 29 months after submission. Operator of record: West Coast Energy.
Planning and build timeline
| Application submitted | 28 August 2008 |
| Permission granted | 26 January 2011 29 months after submission |
| Operational | 27 August 2013 31 months after consent |
Screening a site of your own?
Dumfries and Galloway approves 67% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Barlockhart Moor’s recorded coordinate — swap in your own postcode or coordinates.
Dumfries and Galloway’s record on onshore wind
Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 15.3 | 3.9 km |
Wind Onshore · Operational | 35 | 11 km |
Wind Onshore · Operational | 27.5 | 11.1 km |
Wind Onshore · Operational | 19.5 | 11.7 km |
Wind Onshore · Operational | 239 | 13.7 km |
Wind Onshore · Under Construction | 50.4 | 14.6 km |
How big is Barlockhart Moor?
Barlockhart Moor has a recorded installed capacity of 8.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Barlockhart Moor?
REPD records the operator as West Coast Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Barlockhart Moor approved and built?
The application was submitted on 28 August 2008. Permission was granted on 26 January 2011, 29 months later. The site became operational on 27 August 2013, 31 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4435.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode