Renewable sites › Iron Mountain Howe Moss Drive
Iron Mountain Howe Moss Drive
Iron Mountain Howe Moss Drive is operational in Aberdeen City with a recorded capacity of 0.3 MW, and has been generating since 2020-03-27.
Planning and build timeline
| Application submitted | 2019-06-28 |
| Permission granted | 2019-09-24 3 months after submission |
| Operational | 2020-03-27 6 months after consent |
Aberdeen City’s record on solar
Aberdeen City has decided 13 solar farms and approved 100%, taking a median of 1.5 months. See every solar farm decision in Aberdeen City →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Farburn Place - Battery Energy Storage Facility Battery · Under Construction | 30 | 1.8 km |
Tarbothill Landfill Site Landfill Gas · Operational | 2.2 | 9 km |
Black Dog Landfill Gas · Operational | 2.2 | 10 km |
European Offshore Wind Deployment Centre (EOWDC) (Aberdeen Bay - Demonstration site) Wind Offshore · Operational | 96.8 | 10.9 km |
Ness Energy Project EfW Incineration · Operational | 11.1 | 12.1 km |
Hill of Fiddes Wind Onshore · Operational | 6.9 | 13.9 km |
How big is Iron Mountain Howe Moss Drive?
Iron Mountain Howe Moss Drive has a recorded installed capacity of 0.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Iron Mountain Howe Moss Drive?
REPD records the operator as Iron Mountain. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Iron Mountain Howe Moss Drive approved and built?
The application was submitted on 2019-06-28. Permission was granted on 2019-09-24, 3 months later. The site became operational on 2020-03-27, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7526.