Renewable sites › Foxburrow Farm
Foxburrow Farm
Foxburrow Farm is operational in East Suffolk with a recorded capacity of 8 MW, and has been generating since 2014-10-31.
Planning and build timeline
| Application submitted | 2013-08-22 |
| Permission granted | 2013-11-27 3 months after submission |
| Operational | 2014-10-31 11 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Suffolk’s record on solar
East Suffolk has decided 33 solar farms and approved 97%, taking a median of 3 months. See every solar farm decision in East Suffolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Foxhall Landfill Site Landfill Gas · Operational | 1.2 | 1.4 km |
Stratton Hall Solar Park Solar Photovoltaics · Operational | 11.6 | 4.2 km |
Ipswich Hospital Energy Centre Biomass (dedicated) · Operational | 2.6 | 6.1 km |
University Of Suffolk Campus North Battery · Operational | — | 8.2 km |
Rock Barracks Solar Farm Solar Photovoltaics · Under Construction | 1.5 | 8.8 km |
Lower Ufford Lane Solar Photovoltaics · Operational | 1.1 | 11.4 km |
Bullen Lane - Battery Storage Battery · Under Construction | 100 | 13.5 km |
Bentwaters CHP Biomass (dedicated) · Operational | 4.6 | 13.6 km |
How big is Foxburrow Farm?
Foxburrow Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Foxburrow Farm?
REPD records the operator as UK Sustainable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Foxburrow Farm approved and built?
The application was submitted on 2013-08-22. Permission was granted on 2013-11-27, 3 months later. The site became operational on 2014-10-31, 11 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1480.