Bromborough Dock

Bromborough Dock is an operational 3.7 MW landfill gas site in Wirral, generating since 1 September 1999. REPD does not record the planning grant date. Operator of record: Biffa.

3.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 1999
Landfill Gas
Technology
Biffa
Wirral
Authority
England

Planning and build timeline

Application submittednot recorded
Permission grantednot recorded
Operational1 September 1999

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Wirral: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bromborough Dock’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
30.9 km
Advanced Conversion Technologies · Under Construction
285.2 km
Solar Photovoltaics · Operational
1.27.4 km
Battery · Operational
28.7 km
Battery · Operational
49.98.7 km
Battery · Operational
49.98.7 km
Battery · Operational
208.7 km
Battery · Under Construction
579.1 km

How big is Bromborough Dock?

Bromborough Dock has a recorded installed capacity of 3.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bromborough Dock?

REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bromborough Dock approved and built?

REPD does not record a submission date. REPD does not record a grant date. The site became operational on 1 September 1999.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 657.