Novarly ParcelRenewable sites

Renewable sitesHook Moor

Hook Moor

Hook Moor is operational in Leeds with a recorded capacity of 10.3 MW, and has been generating since 2016-01-15.

10.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-01-15
Wind Onshore
Technology
Banks Renewables
Leeds
Authority
England

Planning and build timeline

Application submitted2008-02-26
Permission granted2011-12-09
45 months after submission
Operational2016-01-15
49 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Peckfield Quarry Landfill Scheme
Landfill Gas · Operational
3.93.3 km
Barnsdale Road Solar Park
Solar Photovoltaics · Under Construction
406.4 km
Kingspan Insulation Solar Installation
Solar Photovoltaics · Operational
57.5 km
Cranswick Country Foods, Seafox Court - Solar Panels
Solar Photovoltaics · Under Construction
0.657.8 km
Monk Fryston Battery Storage
Battery · Under Construction
3207.9 km
Monk Fryston Battery Storage
Battery · Under Construction
577.9 km
Land at Ash Row Farm
Solar Photovoltaics · Operational
58 km
Wothersome Grange Farm House AD - crops
Anaerobic Digestion · Operational
18.2 km

How big is Hook Moor?

Hook Moor has a recorded installed capacity of 10.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hook Moor?

REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hook Moor approved and built?

The application was submitted on 2008-02-26. Permission was granted on 2011-12-09, 45 months later. The site became operational on 2016-01-15, 49 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4658.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council