Peckfield Quarry Landfill Scheme
Peckfield Quarry Landfill Scheme is an operational 3.9 MW landfill gas site in Leeds, generating since 25 January 2000. Planning permission was granted on 22 September 1998, 3 months after submission. Operator of record: Natural Power.
Planning and build timeline
| Application submitted | 30 June 1998 |
| Permission granted | 22 September 1998 3 months after submission |
| Operational | 25 January 2000 16 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Leeds: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Peckfield Quarry Landfill Scheme’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Green Belt — Leeds
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 40 | 3.2 km |
Wind Onshore · Operational | 10.3 | 3.3 km |
Battery · Under Construction | 320 | 5.8 km |
Battery · Under Construction | 57 | 5.9 km |
Landfill Gas · Operational | 5.2 | 7 km |
Solar Photovoltaics · Operational | 5 | 7.7 km |
Solar Photovoltaics · Under Construction | 0.65 | 8 km |
Battery · Operational | 150 | 8.1 km |
How big is Peckfield Quarry Landfill Scheme?
Peckfield Quarry Landfill Scheme has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Peckfield Quarry Landfill Scheme?
REPD records the operator as Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Peckfield Quarry Landfill Scheme approved and built?
The application was submitted on 30 June 1998. Permission was granted on 22 September 1998, 3 months later. The site became operational on 25 January 2000, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 744.