Renewable sites › Monk Fryston Battery Storage
Monk Fryston Battery Storage
Monk Fryston Battery Storage is under construction in North Yorkshire with a recorded capacity of 320 MW.
Planning and build timeline
| Application submitted | 2021-06-23 |
| Permission granted | 2022-12-01 17 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Green Belt — North Yorkshire
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Yorkshire’s record on battery storage
North Yorkshire has decided 29 battery storage schemes and approved 100%, taking a median of 10.5 months. See every battery storage scheme decision in North Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Monk Fryston Battery Storage Battery · Under Construction | 57 | 0.2 km |
Kirkhaw Lane - Battery Storage Energy Battery · Operational | 150 | 3.7 km |
Kirkhaw Lane Battery · Operational | 20 | 4 km |
Ferrybridge Multifuel 2 (FM2) EfW Incineration · Operational | 70 | 4.2 km |
Ferrybridge Multifuel 1 (FM1) EfW Incineration · Operational | 68 | 4.2 km |
Kingspan Insulation Solar Installation Solar Photovoltaics · Operational | 5 | 5.3 km |
Cranswick Country Foods, Seafox Court - Solar Panels Solar Photovoltaics · Under Construction | 0.65 | 5.3 km |
Peckfield Quarry Landfill Scheme Landfill Gas · Operational | 3.9 | 5.8 km |
How big is Monk Fryston Battery Storage?
Monk Fryston Battery Storage has a recorded installed capacity of 320 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Monk Fryston Battery Storage?
REPD records the operator as SSE Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Monk Fryston Battery Storage approved and built?
The application was submitted on 2021-06-23. Permission was granted on 2022-12-01, 17 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 15164.