Planning and build timeline
| Application submitted | 2013-05-28 |
| Permission granted | 2013-10-08 4 months after submission |
| Operational | 2014-03-01 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Dorset
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dorset’s record on solar
Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Verwood Solar Farm Solar Photovoltaics · Operational | 20.4 | 2.4 km |
Mannington Battery Energy Storage System Battery · Under Construction | 49.9 | 2.6 km |
Wedgehill Farm Solar Photovoltaics · Operational | 13 | 3 km |
Chapel Lane Parley Solar Farm Phase 3 Solar Photovoltaics · Operational | 4 | 4.9 km |
Bedborough Farm Solar Photovoltaics · Operational | 7 | 5.3 km |
Chapel Lane Parley Solar Farm Phase 2 Solar Photovoltaics · Operational | 36 | 5.7 km |
Land Adj Harmer Warren Quarry Battery · Under Construction | 10 | 5.8 km |
Hamer Warren Solar Farm Solar Photovoltaics · Under Construction | 23 | 6.1 km |
How big is Homeland Solar Farm?
Homeland Solar Farm has a recorded installed capacity of 13.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Homeland Solar Farm?
REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Homeland Solar Farm approved and built?
The application was submitted on 2013-05-28. Permission was granted on 2013-10-08, 4 months later. The site became operational on 2014-03-01, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1761.