Renewable sites › Homeland Solar Farm
Homeland Solar Farm
Homeland Solar Farm is an operational 13.2 MW solar farm in Dorset, generating since 1 March 2014. Planning permission was granted on 8 October 2013, 4 months after submission. Operator of record: Foresight.
Planning and build timeline
| Application submitted | 28 May 2013 |
| Permission granted | 8 October 2013 4 months after submission |
| Operational | 1 March 2014 5 months after consent |
Screening a site of your own?
Dorset approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Homeland Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Dorset
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dorset’s record on solar
Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 20.4 | 2.4 km |
Battery · Under Construction | 49.9 | 2.6 km |
Solar Photovoltaics · Operational | 13 | 3 km |
Solar Photovoltaics · Operational | 4 | 4.9 km |
Solar Photovoltaics · Operational | 7 | 5.3 km |
Solar Photovoltaics · Operational | 36 | 5.7 km |
Battery · Under Construction | 10 | 5.8 km |
Solar Photovoltaics · Under Construction | 23 | 6.1 km |
How big is Homeland Solar Farm?
Homeland Solar Farm has a recorded installed capacity of 13.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Homeland Solar Farm?
REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Homeland Solar Farm approved and built?
The application was submitted on 28 May 2013. Permission was granted on 8 October 2013, 4 months later. The site became operational on 1 March 2014, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1761.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode